Tuesday, November 8, 2016

11-8-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Cloudy Light Rain  PM Cloudy Light Rain 
Hi 59 Lo 42

Reith Riley Had a concrete crew working on pouring cycle track from Madison to LaSalle on the east side of Michigan. A second crew worked on pouring curb at the North east corner of Main and Western. A third crew picked up miscellanies items on Main Street. A curb crew worked on Saint Joe street from Jefferson to Wayne.

Reith Riley had a prep crew working on placing stone in the curb areas on Main Street on the east side from Jefferson to Colfax. A second prep crew worked on the century center drive to the loading dock and the side walk on Michigan.

Indiana Earth had a crew doing removals at the North west corner of Michigan and LaSalle. They had a second crew working on grading for curb from Washington to Wayne. 

Pemberton Davis had a crew working on setting up street lights on the east side of Main street. They had a second crew working on pouring strain pole foundations on Colfax and saint Joe and a third crew placing conduit on the west side of saint Joe from Colfax to Washington.

Woodruff worked on placing structures on the east side of Saint Joe between Washington and Colfax.

Slussers worked on planting trees on Bartlett and Riverside they then moved to the Bartlett round about.

No comments: