Wednesday, May 31, 2017

5-31-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 68 Lo 48

Reith Riley had no one on site today.

Metro Net tore up to run fiber in front of the Century Center.

Pemberton Davis had a 4 man crew working on the thermal detection at Colfax and MLK. They then went to Main and LaSalle and worked on the push peds. They also worked on the thermo detection at MLK and LaSalle.

Pemberton Davis had a 2 man crew painting the mast arms at the intersection of Michigan and Bronson.

Pemberto Davis had a 4 man crew cutting loops at the intersection of Sample and Main and Sample and Michigan.

Air Marking had a 3 man crew working on Parking stalls and any other miscellaneous work.

Slussers was in and placed sod on Michigan from LaSalle North to Navarre. They then placed it at Bronson and Main Street.

Wissco had a 4 man crew working on irrigation at various locations.



Tuesday, May 30, 2017

5-30-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 76 Lo 48

Reith Riley had no one on site today.

AirMarking had no one on site today.

Pemberton Davis  had a 2 man crew pulling wire at Main and Sample.

Pemberton Davis had a 5 man crew putting in Detector housings at Sample and Michigan. they then went to Lafayette and LaSalle and placed the 5 section heads.

Pemberton Davis had a 4 man loop crew working at Main and Western then they went to Main and Sample.

Wisco had a 4 man crew working on repairs on main and MLK

Slussers not on site today.

5-27-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Cloudy    PM Partly cloudy 
Hi 74 Lo 48

Slussers had a 5 man crew placing sod on MLK from Colfax to LaSalle on the east and west side of the road.

No other work took place today.

Friday, May 26, 2017

5-26-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Cloudy    PM Partly cloudy 
Hi 74 Lo 48

Reith Riley had no one on site today.

Pemberton Davis had a 7 man crew working on Detector Housings at Michigan and Sample until Noon

Wisco had a 4 man crew working on MLK from Wayne to LaSalle 

Airmarking had a 2 man crew working on white detail work at various locations.

A-one was on site to place the yellow center line on the bike path.



Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-26-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Reith Riley: is done, Air Marking will be in to finish up stripping, Slussers will be in to finish sodding and plants, Wisco will be in to fix any irrigation.

2.       Pemberton Davis, Will get Lafayette and LaSalle completed and do any work in the down Town area working out ward. They will get the rest of the loops cut and sealed.

Utility Relocation Issues:
AEP:  Was a no show
1.       Michigan and Indian
2.       Poles on Marion east of Michigan
Robert Henry:
           
Metronet: 
                 
                Transpo: No issues
               
                311
               
                DTSB :

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: Memorial Hospital
Action Items  

1.        Pave drain: have not received any plans on how to remedy the situation  from Structure Point yet. Jitin will call Reith Riley later today.

2.        Chase Tower I will send a formal letter rejecting the acceleration work.

3.       Irrigation, Double Tree, Burger King- Wisco will need to get these repairs taken care of.

4.       Tree grate and Brick Storage the City needs to find  a secure location for these materials

5. Traffic accidents Kara has a meeting with legal later today to discuss these issues

               
Reith Riley Construction Concerns/Questions

City Concerns/Questions

Jitin was going to look into having trees add to the islands between Jefferson and Washington on MLK

I will set up a walk through for June 7th                                        

 Next weekly progress 6-2-17




Thursday, May 25, 2017

5-25-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Cloudy drizzle   PM Partly cloudy 
Hi 74 Lo 48

Pemberton Davis had a 7 man crew working on the detector housings at Sample and Michigan.

Air Marking had a 2 man crew work on parking stalls and Miscillaneous white detail work.

Slussers had a 6 man crew placing sod on Martin Luther King Street from Wayne to LaSalle 

Wednesday, May 24, 2017

5-24-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Cloudy Rain   PM Cloudy Rain 
Hi 68 Lo 48

Rieth Riley had a 6 man crew installing bike racks and doing miscellaneous work.

Rieth Riley had a 3 man crew installing the Bike repair station and cleaning up the service yard.

Slussers had a 4 man crew working on Mulch and grading out for sod.

Wisco had a 4 man crew working on the irrigation on MLK.

Pemberton Davis had a 6 man crew working on detector housings on Sample and Michigan.

Pemberton Davis had a 2 man crew painting Mast Arms on MLK and Monroe and MLK and Western and MLK and Wayne.

Pemberton Davis had a 2 man crew working on wiring the new cabinet at Monroe and Michigan

Airmmarking had a 2 man crew placing bike emblems on Main Street and on Michigan.

Airmarking had a second 2 man crew working on white detail work.  

Tuesday, May 23, 2017

5-23-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain   PM Cloudy Rain 
Hi 68 Lo 48

Reith Riley had a 6 man concrete crew working on Miscilanious areas.

Reith Riley had a 5 man brick crew working on clean up and odds and ends

Wisco had a 3 man crew working on MLK

Airmarking had a 2 man crew come in and do removals.

Pemberton Davis had a 4 man crew working on handholes  at Sample and Michigan. They had a 3 man crew placing signs on MLK.

Slusser had a 2 man crew come in late and work on mulch and top soil.

 Indiana earth not on site today.

State Barricade had 2 guys picking up barrels and cones 

Monday, May 22, 2017

5-22-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny   PM Sunny 
Hi 72 Lo 48

Reith Riley had a 6 man crew staining the concrete drives for the bike path on Main Street from Wayne Street North to Madison.

Reith Riley had a 5 man brick crew cutting brick and sanding them in on Michigan from Wayne to Madison.

Indiana Earth had a 4 man crew placing top soil on MLK from Wayne to Marion and doing general clean up.

Wisco had a 5 man crew working on the irrigation from Wayne street to Washington on MLK.

Airmarking had a 2 man crew placing bike emblomes on Main street and Michigan from Wayne to Marion.

Airmarking had a 2 man crew placing cross hatch and turn arrows at various locations. 

Pemberton Davis had a 2 man crew working on receptacles at the South east quad of Bartlett and Michigan.

Pemberton Davis had a 2 man crew working on Painting at MLK and Western, and MLK and Wayne/Jefferson

Pemberton Davis had a 4 man crew working at MLK and Monroe placing thermo detection and wiring.

AEP was in and hooked power up at Bronson and Main.

5-21-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 3.5/10
AM Cloudy Rain   PM Cloudy Rain 
Hi 68 Lo 48

Pemberton Davis worked on signs and Sample and Michigan intersection.\

At some point over night a tree and light pole was struck on MLK between Colfax and LaSalle.

5-20-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 3.5/10
AM Cloudy Rain   PM Cloudy Rain 
Hi 68 Lo 48

Pemberton Davis worked at Sample and Michigan placing hand holes and Conduit.

Friday, May 19, 2017

5-19-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 3.5/10
AM Cloudy Rain   PM Cloudy Rain 
Hi 68 Lo 48

Rain moved in at 11:30

Reith Riley had a 3 man crew staining concrete drives for the bike path. They had a 3 man crew route and sealing cracks. They had a 3 man crew doing miscellaneous concrete.

Reith Riley had a 9 man crew sanding and adjusting brick on Main Street.

Reith Riley had a 3 man crew working on punch list items and cleaning up North of LaSalle

Wisco had a 4 man crew working on MLK 

Pemberton Davis had a 4 man crew cutting loops on Main Street and Western

Pemberton Davis had a 3 man crew working on outlet at Bartlett and Michigan.

Pemberton Davis had a 5 man crew working on Detector Housings at Sample and Michigan. 

Airmarking had a 2 man crew finish the green thermo and worked on the bike symbols.

Airmarking had a 2 man crew working on white detail work at various locations.


Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-19-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Rieth Riley will finish the miscellaneous items that they have Bike Racks, water fountain, benches, Trashcans. They will begin to work on the punch list, Stain the concrete and do general clean up. Airmarking will be in to work on stripping. Slussers will work on sod and mulch. Wisco will work on finishing the irrigation.

2.       Pemberton Davis will finish the Receps by the hospital. They will have the rest of the loops and detector housings placed. They will be working on signs. They will continue to paint mastarms

Utility Relocation Issues:
AEP: 
1.       Michigan and Indiana This will be handled with Tony Macia
2.       Monroe and Michigan hooked up today
3.       Bronson and Main scheduled for Hook up Monday due to rain
4.       Bronson and Michigan Hooked up today
5.       Poles on Marion east of Michigan Dave will check on
Robert Henry:
          
Metronet: 
                No show 
                Transpo:
                                No questions
                311
                                No Show
                DTSB :
                                No Show
Utilities Q/A

INDOT: Questions:    No Show

Stakeholder Questions: Memorial Hospital
Action Items  
1.       Thermo detection Change order- Reith Riley still wants full extension or they can deliver the material as soon as it comes in.

2.       Pave drain: Rieth Riley can have the Pave Drain reset work done next week if the City wants to pay the time and material to fix otherwise this can go to the punch list and discussed further on who is responsible. Rieth Riley will pay for an independent 3rd party to investigate the integrity of the design and the integrity of the installation of the pave drain.

3.       Chase Tower: Rieth Riley cannot commit to getting this done the longer this goes without a decision

               
Reith Riley Construction Concerns/Questions

Reith Riley wants  a formal written response to the action items listed above.

City Concerns/Questions
Will the fiber to the traffic signals be installed next week? YES
The tops of the curb need to be painted yellow at Colfax and MLK East side.                                        
 Next weekly progress 5-26-17