Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 72 Lo 48
Reith Riley had a 6 man crew staining the concrete drives for the bike path on Main Street from Wayne Street North to Madison.
Reith Riley had a 5 man brick crew cutting brick and sanding them in on Michigan from Wayne to Madison.
Indiana Earth had a 4 man crew placing top soil on MLK from Wayne to Marion and doing general clean up.
Wisco had a 5 man crew working on the irrigation from Wayne street to Washington on MLK.
Airmarking had a 2 man crew placing bike emblomes on Main street and Michigan from Wayne to Marion.
Airmarking had a 2 man crew placing cross hatch and turn arrows at various locations.
Pemberton Davis had a 2 man crew working on Painting at MLK and Western, and MLK and Wayne/Jefferson
Pemberton Davis had a 4 man crew working at MLK and Monroe placing thermo detection and wiring.
AEP was in and hooked power up at Bronson and Main.