Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 3.5/10
AM Cloudy Rain PM Cloudy Rain
Hi 68 Lo 48
Rain moved in at 11:30
Reith Riley had a 3 man crew staining concrete drives for the bike path. They had a 3 man crew route and sealing cracks. They had a 3 man crew doing miscellaneous concrete.
Reith Riley had a 9 man crew sanding and adjusting brick on Main Street.
Reith Riley had a 3 man crew working on punch list items and cleaning up North of LaSalle
Wisco had a 4 man crew working on MLK
Pemberton Davis had a 4 man crew cutting loops on Main Street and Western
Pemberton Davis had a 3 man crew working on outlet at Bartlett and Michigan.
Pemberton Davis had a 5 man crew working on Detector Housings at Sample and Michigan.
Airmarking had a 2 man crew finish the green thermo and worked on the bike symbols.
Airmarking had a 2 man crew working on white detail work at various locations.
Meeting Minutes
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Rieth Riley will finish the miscellaneous items
that they have Bike Racks, water fountain, benches, Trashcans. They will begin
to work on the punch list, Stain the concrete and do general clean up. Airmarking
will be in to work on stripping. Slussers will work on sod and mulch. Wisco
will work on finishing the irrigation.
2.
Pemberton Davis will finish the Receps by the
hospital. They will have the rest of the loops and detector housings placed. They
will be working on signs. They will continue to paint mastarms
Utility Relocation Issues:
AEP:
1.
Michigan and Indiana This will be handled with Tony
Macia
2.
Monroe and Michigan hooked up today
3.
Bronson and Main scheduled for Hook up Monday
due to rain
4.
Bronson and Michigan Hooked up today
5.
Poles on Marion east of Michigan Dave will check
on
Robert Henry:
Metronet:
No show
Transpo:
No
questions
311
No
Show
DTSB :
No Show
Utilities Q/A
INDOT: Questions: No Show
Stakeholder Questions:
Memorial Hospital
Action Items
1.
Thermo detection Change order- Reith Riley
still wants full extension or they can deliver the material as soon as it comes
in.
2.
Pave drain: Rieth Riley can have the Pave
Drain reset work done next week if the City wants to pay the time and material
to fix otherwise this can go to the punch list and discussed further on who is responsible.
Rieth Riley will pay for an independent 3rd party to investigate the
integrity of the design and the integrity of the installation of the pave
drain.
3.
Chase Tower: Rieth Riley cannot commit to
getting this done the longer this goes without a decision
Reith Riley Construction
Concerns/Questions
Reith Riley wants a formal
written response to the action items listed above.
City
Concerns/Questions
Will the fiber to the traffic signals be installed next week?
YES
The tops of the curb need to be painted yellow at Colfax and
MLK East side.
Next weekly progress 5-26-17
No comments:
Post a Comment