Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 68 Lo 47
Reith Riley has a 6 man concrete crew working on the drive on the east side of Main Street between South Street and Monroe. They then worked on trash can pads
reith riley had a 4 man brick crew working on Michigan between LaSalle and Washington on theeast side of the road.
reith Riley had a 4 man brick crew working on the west side of Main Street from Western to Colfax.
Pemberton Davis had a 3 man crew placing signs
Pemberton Davis had a 2 man crew painting mast arms.
Pemberton Davis had a 4 man crew working on Detector Housings at Main and Colfax
Slussers had a 3 man crew placing top soil on MLK from LaSalle to Wayne
Airmarking had a 3 man crew placing green bike on Monroe and Main Street.
Airmarking had a 3 man crew placing long line throughout the city.;
Meeting Agenda
Reith Riley has a 6 man concrete crew working on the drive on the east side of Main Street between South Street and Monroe. They then worked on trash can pads
reith riley had a 4 man brick crew working on Michigan between LaSalle and Washington on theeast side of the road.
reith Riley had a 4 man brick crew working on the west side of Main Street from Western to Colfax.
Pemberton Davis had a 3 man crew placing signs
Pemberton Davis had a 2 man crew painting mast arms.
Pemberton Davis had a 4 man crew working on Detector Housings at Main and Colfax
Slussers had a 3 man crew placing top soil on MLK from LaSalle to Wayne
Airmarking had a 3 man crew placing green bike on Monroe and Main Street.
Airmarking had a 3 man crew placing long line throughout the city.;
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Reith Riley will close Main Street on Monday and
detour traffic down Michigan from South to Sample Street. They will complete
all concrete work and the guard rail on Main between Bronson and South. They
will finish all the brick on the contract. Landscapers will be in to do plants
on MLK along with Wisco to work on the irrigation.
2.
Pemberton Davis will be working on the detector
housings on Main Street from Monroe to Sample. They will have a crew placing
signs. A crew will be in to cut loops in the downtown area. Pemberton will also
work on the reseps at Bartlett.
Utility Relocation Issues:
AEP:
1.
Power at Western and Michigan AEP will work on getting
this next week
2.
Power at Monroe and MLKAEP will work on getting this
next week
3.
Michigan and Indiana
4.
Poles on Marion east of Michigan Dave will get
with AT@T to get these removed.
Robert Henry:
Metronet:
Transpo: Sign Placement – No more transpo
signs should show up on this job, we will relocate the current ones.
311
DTSB :
Utilities Q/A
INDOT: Questions:
Stakeholder Questions:
Memorial Hospital
Action Items
1.
Thermo detection Change order Reith Riley
want a full time extension or have the material purchased. The city would like
to have just the line items extended.
2.
Pave drain : it will cost roughly 52
dollars a sys to rest the pave drain. Reith Riley feels they installed it per
the manufactures recommendations. City will weigh its options
3.
Signs : parking signs will need to be
corrected to the 2 hour. An additional yield will need to go up at Marion.
Reith Riley Construction
Concerns/Questions
Josh will need to be present when the work at Mrs. Kerrs
home is done.
City
Concerns/Questions
The green thermos going down at the bike ramps, has the city
concerned over the burnt look, the city would like to have it power washed to
turn it green.
Traffic marking issues at Main and Calvert, North Bound Main
and Sample and MLK south of Wayne Bike symble
Next weekly progress 5-19-17