Wednesday, May 10, 2017

5-10-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Partly Sunny  PM Cloudy 
Hi 68 Lo 50

Reith Riley had a 5 man concrete crew pour the side walk to the parking area on the South east corner of Marin and Michigan. They then poured the ramp at Michigan and MLK.

Reith Riley had a 8 man brick crew working on Main Street from Western to Washington east and west side. They also rest the pave drain on the west side of Main from Wayne to Western.

Reith Riley had a 3 man prep crew remove the ramp at the Morris and they then worked on clean up threw out the project.

Indiana earth had a 3 man crew working on topsoil from Washington to Jefferson on MLK.

Pemberton Davis had a 2 man crew working on Main Street painting Mast arms at Wayne and Main.

Pemberton Davis had a 2 man crew working on signs. they had a man working on lighting north of Bartlet on the west side. They also had a 2 man crew working on the intersection of Jefferson and MLK.

Pemberton Davis had 2 men working on the lights at the via-docks.  

Airmarking had a 3 man crew working on green thermo on main street from LaSalle to Western

Airmarking had a 3 man crew working on detail work stop bars and cross walks at Navarre and Michigan and on Main and sample.

Airmarking had a 3 man crew placing long line thermo throughout the downtown area.

Airmarking had another 3 man crew placing bike symbols on the side streets.