Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Sunny  PM Sunny
Hi 55 Lo 30

Reith Riley had a 5 man Concrete crew pouring the ramps at Main and Monroe South West Corner. They then worked on cutting out for Bike posts.

Reith Riley had a second 5 man Concrete crew working on MLK doing Miscellaneous concrete work  

Reith Riley had a 6 man Brick crew working on MLK west side between Jefferson and Colfax

Reith Riley had a 6 man Asphalt crew paving the surface on the parking lot at the South East corner of Marion and Michigan.They then went and patched the parking lot at the corner of Main and Western North West side.

Pemberton Davis had a 7 man crew working on Detector Housing on Main and Jefferson and Main and Wahington.

Air Marking had a 3 man detail crew working on Cross walks at western and Main and Monroe and Main.

Air Marking had a 3 Man detail crew working on bike symbols on Michigan from Sample to Western

Air Marking had a 3 man crew working on green epoxy on Main Street from Colfax to Western on the west and east side of the road.

Indiana Earth had a 3 man crew do removals at Angela and Michigan and then worked on Top Soil on MLK from Wayne to Washington on the east side of the road.