Wednesday, May 17, 2017

5-17-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 85 Lo 61

Reith Riley had an 8 man Concrete crew working on Main Street south Bound Lane between Bronson and South Street.

Reith Riley had a 3 man brick crew working on MLK at the South west corner of MLK and Jefferson. They then went to the South east corner.

reith Riley had a 3 man brick crew working on the North east corner of Michigan and LaSalle

Indiana Earth had a 3 man crew working on removals under the bridge on main street between Bronson and South Street. 

C-Tech had a 3 man crew working on the attenuators on Main Street.

Slussers had a 4 man crew planting trees and shrubs on MLK between Colfax and Wayne.

Wisco had a 4 man crew working on irrigation drip on MLK from LaSalle to Wayne

Pemberton Davis had a 4 man crew working on Detector Housings at Sample and Main.

Pemberton Davis had a 2 man crew painting mast arms at Western and Main, and Monroe and Main.

Pemberton Davis had a 4 man crew cutting loops on main street at Washington and then at Colfax.

AirMarking had a 2 man crew working on white detail work at various locations.

AirMarking had a 2 man crew working  the green epoxy and epoxy bike symbols.