Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 85 Lo 61

Reith Riley had an 8 man Concrete crew working on various areas throughout the project (incidental concrete).

Reith Riley had a 8 man crew working on sanding brick and relaying brick on main street.

Reith Riley had a 3 man crew cutting brick on MLK from Washington to Jefferson on the east side.

Pemberton Davis had 2 man crew painting mast arms at Michigan and Monroe and Michigan and western.

Pemberton Davis had a 2 man crew working on the electric at the hospital.

Pemberton Davis had a 4 man crew working on detector housings at Sample and Main and Sample and Michigan.

Pemberton Davis had a 4 man crew working on Loops at Main and western, and Main and Washington, and Main and Monroe

Wisco had a 5 man crew working on irrigation on MLK 

Slussers had a 5 man crew working on plantings on MLK 

Airmarking had a 2 man detail crew working on green thermo then they switched to bike emblems.

Airmarking had a 2 man crew working on white arrows and only s and 4 inch line.cross hatch and parking stalls.