Wednesday, May 3, 2017

5-3-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny 
Hi 58 Lo 42

Reith Riley had a 8 man concrete crew on site and fifnished the side walk from Wayne to Jefferson on the east side of MLK. They then worked the North East Corner of Jefferson and MLK

Reith Riley had a 6 man brick crew working from Wayne to Jefferson on the east side of MLK. They also worked on the west side of MLK from Colfax to Washington. 

Reith Riley had a 3 man prep crew working on grading the lot north of McDonald's. 

Reith Riley had a 6 man Asphalt crew in doing western and Main, LaSalle and main. The patch on MLK and the parking Lot North of McDonald.

Air Marking had a 3 man crew working on the Green epoxy in front of the Colfax Garage and the Wayne street Gaurage. 

AirMarking had a 2 man crew placing cross walk at Michigan and Monroe and Michigan and Wayne

Pemberton Davis had a 2 man crew painting the mast arms at Washington and Main.

Pemberton Davis had a 6 man crew placing detector housings at Main and Western, Main and Wayne, and Main and Jefferson.

Pemberton Davis had a 4 man crew cutting loops at Main and Monroe, and Main and western.

Slussers had a 4 man crew working on placing topsoil on MLK in the Islands from Wayne to LaSalle. They then went on to main street and straightened up trees.