Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Cloudy Rain PM Mostly Cloudy Rain
Hi 63 Lo 52
Reith Riley had a 8 man crew pouring concrete at the North west corner of Wayne and MLK. They also poured the South east corner of Jefferson and MLK.
Reith Riley had a 4 man asphalt crew milling and prepping areas to pave.
Reith Riley had a 6 man brick crew working on MLK between Colfax and Washington grading out for brick. They also worked on the east side of MLK from Washington to Wayne.
Pemberton Davis had a 7 man crew working on detector housings on Main Street and Wayne, Main and western and they worked on Bronson and Main and Bronson and MLK.
Pemberton Davis also had a 2 man crew painting mast arms at Main and Washington.
Pemberton Davis had another contractor on site cutting loops at Main and Bronson and Main and south Street.
AirMarking had a 3 man crew working on placing the green thermo down at Madison on Main and Michigan. Thye then moved to
Reith Riley had a 8 man crew pouring concrete at the North west corner of Wayne and MLK. They also poured the South east corner of Jefferson and MLK.
Reith Riley had a 4 man asphalt crew milling and prepping areas to pave.
Reith Riley had a 6 man brick crew working on MLK between Colfax and Washington grading out for brick. They also worked on the east side of MLK from Washington to Wayne.
Pemberton Davis had a 7 man crew working on detector housings on Main Street and Wayne, Main and western and they worked on Bronson and Main and Bronson and MLK.
Pemberton Davis also had a 2 man crew painting mast arms at Main and Washington.
Pemberton Davis had another contractor on site cutting loops at Main and Bronson and Main and south Street.
AirMarking had a 3 man crew working on placing the green thermo down at Madison on Main and Michigan. Thye then moved to