Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Cloudy Rain PM Cloudy Rain
Hi 68 Lo 48
Rieth Riley had a 6 man crew installing bike racks and doing miscellaneous work.
Rieth Riley had a 3 man crew installing the Bike repair station and cleaning up the service yard.
Slussers had a 4 man crew working on Mulch and grading out for sod.
Wisco had a 4 man crew working on the irrigation on MLK.
Pemberton Davis had a 6 man crew working on detector housings on Sample and Michigan.
Pemberton Davis had a 2 man crew painting Mast Arms on MLK and Monroe and MLK and Western and MLK and Wayne.
Pemberton Davis had a 2 man crew working on wiring the new cabinet at Monroe and Michigan
Airmmarking had a 2 man crew placing bike emblems on Main Street and on Michigan.
Airmarking had a second 2 man crew working on white detail work.
Rieth Riley had a 6 man crew installing bike racks and doing miscellaneous work.
Rieth Riley had a 3 man crew installing the Bike repair station and cleaning up the service yard.
Slussers had a 4 man crew working on Mulch and grading out for sod.
Wisco had a 4 man crew working on the irrigation on MLK.
Pemberton Davis had a 6 man crew working on detector housings on Sample and Michigan.
Pemberton Davis had a 2 man crew painting Mast Arms on MLK and Monroe and MLK and Western and MLK and Wayne.
Pemberton Davis had a 2 man crew working on wiring the new cabinet at Monroe and Michigan
Airmmarking had a 2 man crew placing bike emblems on Main Street and on Michigan.
Airmarking had a second 2 man crew working on white detail work.
No comments:
Post a Comment