Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Mostly Sunny
Hi 76 Lo 48
Reith Riley had no one on site today.
Pemberton Davis had a 2 man crew pulling wire at Main and Sample.
Pemberton Davis had a 5 man crew putting in Detector housings at Sample and Michigan. they then went to Lafayette and LaSalle and placed the 5 section heads.
Pemberton Davis had a 4 man loop crew working at Main and Western then they went to Main and Sample.
Wisco had a 4 man crew working on repairs on main and MLK
Slussers not on site today.