Friday, May 26, 2017

5-26-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 8/10
AM Cloudy    PM Partly cloudy 
Hi 74 Lo 48

Reith Riley had no one on site today.

Pemberton Davis had a 7 man crew working on Detector Housings at Michigan and Sample until Noon

Wisco had a 4 man crew working on MLK from Wayne to LaSalle 

Airmarking had a 2 man crew working on white detail work at various locations.

A-one was on site to place the yellow center line on the bike path.



Meeting Minutes
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
5-26-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Reith Riley: is done, Air Marking will be in to finish up stripping, Slussers will be in to finish sodding and plants, Wisco will be in to fix any irrigation.

2.       Pemberton Davis, Will get Lafayette and LaSalle completed and do any work in the down Town area working out ward. They will get the rest of the loops cut and sealed.

Utility Relocation Issues:
AEP:  Was a no show
1.       Michigan and Indian
2.       Poles on Marion east of Michigan
Robert Henry:
           
Metronet: 
                 
                Transpo: No issues
               
                311
               
                DTSB :

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: Memorial Hospital
Action Items  

1.        Pave drain: have not received any plans on how to remedy the situation  from Structure Point yet. Jitin will call Reith Riley later today.

2.        Chase Tower I will send a formal letter rejecting the acceleration work.

3.       Irrigation, Double Tree, Burger King- Wisco will need to get these repairs taken care of.

4.       Tree grate and Brick Storage the City needs to find  a secure location for these materials

5. Traffic accidents Kara has a meeting with legal later today to discuss these issues

               
Reith Riley Construction Concerns/Questions

City Concerns/Questions

Jitin was going to look into having trees add to the islands between Jefferson and Washington on MLK

I will set up a walk through for June 7th                                        

 Next weekly progress 6-2-17




No comments: