Tuesday, May 23, 2017

5-23-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain   PM Cloudy Rain 
Hi 68 Lo 48

Reith Riley had a 6 man concrete crew working on Miscilanious areas.

Reith Riley had a 5 man brick crew working on clean up and odds and ends

Wisco had a 3 man crew working on MLK

Airmarking had a 2 man crew come in and do removals.

Pemberton Davis had a 4 man crew working on handholes  at Sample and Michigan. They had a 3 man crew placing signs on MLK.

Slusser had a 2 man crew come in late and work on mulch and top soil.

 Indiana earth not on site today.

State Barricade had 2 guys picking up barrels and cones 