Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy PM Cloudy
Hi 58 Lo 47
Reith Riley had a 6 man concrete crew working on pouring the ramp at Angela and Michigan. They then poured the ramp at the church on Main between LaSalle and Madison.
Reith Riley had a 6 man brick crew working in front of the Century Center.
Reith Riley had a 5 man brick crew working on the west side of Main street from Washington to Wayne.
Reith Rily had a 3 man prep crew removing the sidewalk at the church and cleaning up through out the job.
Pemberton Davis had a 5 man crew working on Detector Housing on Main and Washington and Main and Colfax. T
Pemberton Davis had a man working on a placing signs.
Pemberton Davis had a man working on a placing signs.
Pemberton Davis had a 2 man crew painting Mast arms on Main and Jefferson and Main and Wayne.
Slussers had a 3 man crew placing top soil on MLK from Wayne to LaSalle
Wisco had a 4 man crew working on the irrigation from LaSalle to Wayne on MLK
Airmarking had a 3 man crew working on green thermo on MLK from Western to Jefferson.
Airmarking had a 3 man detail crew working on cross walks and stop bars.
Airmarking had a 3 man detail crew working on cross walks and stop bars.