Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 85 Lo 61
Reith Riley had a 8 man concrete crew working under the bridge on Main Street between South and Bronson Street.
Reith Riley had a 8 man Brick crew working on Main Street at Western and Colfax. They then went to MLK and worked on cutting brick.
Induiana Earth had a 4 man crew placing top soil on MLK from LaSalle to Jefferson.
Wisco had a 4 man crew working on MLK from LaSalle to Jefferson.
Pemberton Davis had a 2 man crew working on Painting at Main and Western and Main and Monroe.
Pemberton Davis had a 4 man crew working on detector housings at Sample and Main and Sample and Michigan.
Pemberton Davis had a 4 man crew cutting loops at Jefferson and Main.
AirMarking had a 2 man crew placing epoxy red and bike symbols.
AirMarking had a 2 man crew doing thermo detail work,