Monday, May 15, 2017

5-15-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 82 Lo 51

State Barricade closed Main Street North Bound at 7 am this morning.

Reith Riley had a 5 man concrete crew pouring trash can pads and doing miscellaneous work. 

Reith Riley had a 3 man brick crew working on MLK at Jefferson on the west side.

Reith Riley had a 4 man brick crew working at the intersection of Western and Main.

Reith Riley had a 5 man crew working on sanding in brick on MLK they then wen to Main Street.

Reith Riley had a 3 man crew placing brick at MLK and Michigan.

Indiana Earth had a 3 man crew working on removals under the via dock on Main Street. Then placing top soil on MLK

Hardcore cut for the Indiana earth removals.

Pemberton Davis had a 4 man crew cutting loops on Main and Wayne and on Mai and Jefferson

Pemberton Davis had a 2 man crew wiring the lights under the via dock on Main Street

Pemberton Davis had a 2 man crew painting Mast arms at western and Main and at Wayne and Main.

Pemberton Davis had a 2 man crew pulling wire to the detector housings on Main Street from Western to Colfax.

Pemberton Davis had a 4 man crew placing detector housings at Monroe and Main then sample and Main.

Pemberton Davis had a man working on signs all over.

Slussers had  a 5 man crew working on planting trees and plants on MLK from Wayne to LaSalle.

Wisco had a 4 man crew working on MLK from Wayne to LaSalle following up Slussers. 