Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain PM Cloudy windy sprinkles
Hi 64 Lo 50
Reith Riley had a concrete crew working on the South East corner of MLK and Jefferson and infront of the centery center.
They had a 6 man brick crew working on MLK on the east side between Washington and Colfax.
Pemberton Davis had a 7 man crew adjusting the man hole on the east side of MLK between Colfax and LaSalle, They then went to Bronson and Main and worked on push peds and Tesco. Then to Bronson and Michigan and worked on the tesco and push peds.
Airmarking was not on site due to the weather.
Indiana Earth not on site.
No comments:
Post a Comment