Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy PM Cloudy
Hi 58 Lo 42
Reith Riley had a 5 man concrete crew working on the North west and South West corner of Western and Michigan.
Reith Riley had another 5 man concrete crew working on the North East corner of Jefferson and MLK.
Reith Riley had a 3 man prep crew working on the South East corner of MLK and Washington. They then moved on to cleaning up the MLK Area.
Reith Riley had a 5 man brick crew placing brick on MLK from Jefferson to LaSalle on the east side of the road.
Air marking was a no show.
Indiana earth was not on site
Slussers had a 3 man crew planting trees on Main Street in various locations.
Pemberton Davis had a 7 man crew working on the South West corner of Colfax and Michigan placing a tesco foundation. They also placed DHs on Monroe and Western at Main Street.
Meeting Minutes
Reith Riley had a 5 man concrete crew working on the North west and South West corner of Western and Michigan.
Reith Riley had another 5 man concrete crew working on the North East corner of Jefferson and MLK.
Reith Riley had a 3 man prep crew working on the South East corner of MLK and Washington. They then moved on to cleaning up the MLK Area.
Reith Riley had a 5 man brick crew placing brick on MLK from Jefferson to LaSalle on the east side of the road.
Air marking was a no show.
Indiana earth was not on site
Slussers had a 3 man crew planting trees on Main Street in various locations.
Pemberton Davis had a 7 man crew working on the South West corner of Colfax and Michigan placing a tesco foundation. They also placed DHs on Monroe and Western at Main Street.
Meeting With:
|
|
Meeting Date:
|
|
Regarding:
|
|
Construction and
Utilities
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Reith Riley In the up coming week plans on
finishing concrete sidewalk and cycle track. They will continue to work on
Brick pavers. They will have the asphalt crew on site to button up any work and
pave the parking lot north of McDonalds. Slussers will be on site working on
Landscape.
2.
Pemberton Davis will start cutting loops on
Monday starting at Bronson and Main Street working north. They will close down
the side streets as needed to cut the loops. Tanner will meet with Toy on
Monday and develop a plan. The side streets should be closed for only a couple
of hour’s hat a time. They will continue to work on Michigan street traffic
signals.
Utility Relocation Issues:
AEP:
1.
Power at Western and Michigan- Once Phil
contacts AEP this work will get scheduled
2.
Power at Monroe and Michigan Once Phil contacts
AEP this work will get scheduled
3.
Both Bronson Streets Once Phil contacts AEP this
work will get scheduled
4.
Michigan and Indiana Once Phil contacts AEP this
work will get scheduled
Robert Henry:
1.
Manhole lid at Main and LaSalle This work will be completed this weekend.
Metronet: No Show
Transpo No Show
311:
DTSB : Planters we will met
on Monday and go over placement. DTSB will have the trashcans removed that were
determined to be in undesired locations.
Utilities Q/A
INDOT: Questions:
Stakeholder Questions:
Memorial Hospital:
1.
Trees leaning need fixed on Bartlett
2.
Who is mowing the grass- The hospital will need
to if they want it to be maintained properly.
3.
Water Valve in yard at Bartlett and Michigan
needs adjusted so that it isn’t hit by the mower.
4.
Edging by dumpster needs addressed
5.
Dead trees at Bartlett and Main need repaired
6.
Sprinkler system will be turned on by Wisco and
meters will have hospital locks on them
Action Items
1.
Trash can locations: Locations of trash
cans were determined this last week
2.
Cycle track Markings; have been ordered
need a change order yet.
3.
Sign for Jefferson Street: the handicap
parking sign needs installed ASAP.
4.
Guardrail Change order it appears the guardrail
will be in next week and the work will start mid-May and be completed before
the first of June.
5.
Thermo detection Change order: thermos
detection delivery does not appear to be coming in before the 2nd
week of June, and the change order is still unsigned.
6.
Pave drain: the City will have an internal
meeting and this item is still not resolved
7.
Chase Tower is still under discussion
8. Walk
Through – for the area North of LaSalle will be held Thursday May 11 at 1 pm
Reith Riley Construction
Concerns/Questions
City
Concerns/Questions:
The area between LaSalle and Madison on Main need to be
reviewed for acceptance so a bus shelter can be placed.
Next weekly progress 5-5-17
No comments: