Tuesday, April 25, 2017

4-25-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 83 Lo 51

Reith Riley had a 8 man concrete crew working on pouring the ramps and curbs on the North east corner of Washington and MLK. once they finished that they moved to the south east corner of MLK and Washington and then to the North East corner of MLK and Jefferson.

Reith Riley had a 3 man brick crew working on the east side of MLK between Colfax and LaSalle pacing bike pavers. 

Pemberton Davis had a 7 man crew placing detector housings on Main Street and Western, Main Street and Jefferson and they also placed foundations for push peds at Wahington and MLK.

Pemberton Davis had a 3 man crew painting mastarms at Clofax and Main and Wahsington and Main.

AirMarking had a 3 man detail crew working on various locations threw out the job. 
They had a 3 man long line crew working in various locations.
They had a 3 man epoxy crew working in various locations.

Indiana Earth had a 3 man crew doing removals of foundations on MLK from Wayne to Washington. They also worked on grading out for brick in various locations.