Monday, April 10, 2017

4-10-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain  PM Cloudy Rain 
Hi 74 Lo 52

Reith Riley had a 9 man concrete crew pour the South West and South east corners of South Street and Michigan. once the concrete was poured a brief rain came and they had to refinish the side walk. They then moved to the South west corner of Washington and MLK and the South East Corner of MLK.

Reith Riley had a second crew working on the brick and stone on the South West corner of Main and Washington. 

Wisco worked on the east side of MLK between LaSalle and Colfax with a 5 man crew 

Pemberton Davis worked on the intersection of Wayne and MLK placing conduit and foundations on the North West, North East and South East corners. They also worked on the South West corner of Western and MLK.