Thursday, April 13, 2017

4-13-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Land scape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 2/10
AM Cloudy Rain 9:00 am  PM Cloudy Rain 
Hi 55 Lo 43

Reith Riley had a 9 man concrete crew forming at the South East corner of Navarre and Michigan, then they went to the South west corner of MLK and LaSalle. They got rained out at 10 am.

Reith Riley had a 3 man prep crew working on the South East corner of Navarre and Michigan. They then went to the South East corner of Colfax and MLK.

Reith Riley had a 3 man crew working on  sanding in the brick on Main Street from Jefferson to Western on the west side.

Pemberton Davis had a 7 man crew placing conduit on the east side of Michigan from Bartlett to Navarre. They also had a 2 man crew pushing conduit on the east side of Michigan from the River bridge to Bartlett street. They also dug for push peds on the south East corner of Michigan and Navarre.

Wisco worked on installing the new irrigation on Saint Joe/MLK from Washington to Wayne Street on the east side. They also had to go to Navarre and Michigan to do repairs. 