Wednesday, April 12, 2017

4-12-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Land scape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 6/10
AM Sunny  PM Mostly Sunny 
Hi 60 Lo 33

reith Riley had a 3 man prep crew working on the South West corner of LaSalle and MLK. They also worked at the Milton House Drive and the Corner of MLK and Wayne.

Reith Riley had a 3 man brick crew working on the north West and South west corner of Wayne and Main

Reith Riley had a 8 man concrete crew pour the drive to the Milton house on Marion Street that had been damaged by Indiana Earth.

Indiana Earth had a 3 man crew working on removing the sidewalk and ramps at the South East and South west corners of Michigan and Navarre.

Wisco had a 3 man crew work on the irrigation on the east side of MLK from Washington to Wayne.

Pemberton Davis had a 7 man crew work on the intersection of Monroe and MLK , Wayne and MLK and Washington and MLK. in the afternoon they worked on the conduit on the east side of Michigan between Navarre and Bartlett.