Wednesday, April 26, 2017

4-26-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Mostly Sunny
Hi 84 Lo 61

Reith Riley had a 7 man concrete crew working on pouring the sidewalk on the east side of Saint Joe between Wayne and Jefferson. they then left the job for a couple hours to pour curb by the county building on Jefferson and then returned and formed up at the entrance to the Century Center.

Reith Riley had a 6 man brick crew working on Saint Joe Street between LaSalle and Colfax on the east side of the street.

Indiana Earth had a 3 man crew working on cleaning up and cutting grade for the parking lot just North of McDonalds on Michigan.

Airmarking had a 3 man crew placing detail work between Wayne and Marion on Michigan and Main.

Airmarking had a 3 man crew doing layout and doing removals on Michigan at Sample

Airmarking had a 3 man crew placing the Share arrows and bike symbols between Ewing and Broadway on Michigan.

Airmarking had a 3 man crew placing the epoxy at the intersection of Saint Joe and Colfax.

Pemberton Davis had a 7 man crew work on the walk waits at Navarre and Michigan. They then went to Colfax and Main and worked on the walk Waits and pulled wire.

Pemberton Davis had a 2 man crew painting mast arms at Main and Colfax, they then moved to Main and washington