Tuesday, April 18, 2017

4-18-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Land scape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny 
Hi 76 Lo 42

Reith Riley had a 9 man Concrete crew working at the intersection of Colfax and Saint Joe Street. They poured the North West Corner and the lower portion of the South east Corner. They also poured the concrete pavement on the South west and North east corners.

Reith Riley had a 3 man prep crew working on the South East corner of Wayne and Saint Joe. They then moved to the west side of Saint Joe and prepped for side walk from Wayne Street to Jefferson.

Reith Riley had a 7 man crew working on placing brick on the North East and North West corner of Wayne and Main. They then moved to the South East corner of Washington and Main in front of TCU.

Pemberton Davis had a 6 man crew working on placing conduit on the west side of Saint Joe and pulling Wire from Wayne Street to Jefferson Street. They also had a man wiring lights north of Bartlett on Michigan east and west side.

Airmarking had a 3 man crew working on crosswalks, arrows, and onlys on Colfax, Washington and Jefferson street.

Wisco had a 4 man crew working on Saint Joe Street from Jefferson to Wayne street on the east side of the road.

Indiana Earth was not onsite today.   

No comments:

Post a Comment