Reith Riley had a 9 man concrete crew working on the the sidewalk and ramps on the South East corner of Martin Luther King and Washington Street. They then moved to the North west corner of MLK and Washington, and they finished up at the North west corner of Monroe and Michigan.
Reith Riley had a 3 man crew working on the Brick on Main street from Washington to Jefferson on the west side of the road
Reith Riley had a 3 man crew working on prepping and clean up the South East and South west corners of MLK and LaSalle and at various locations throughout the project.
Pemberton Davis had a 7 man crew working on push ped foundations at Colfax and MLK. Light Foundations at MLK and Wayne and conduit on the south west corner of Jefferson and MLK.
Wisco worked on the irrigation on the east side of MLK from LaSalle to Washington.
Indiana Earth worked on removals at the North West corner of MLK and Washington, the Milton home and the intersection of Navarre and Michigan.