Tuesday, April 11, 2017

4-11-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Foggy  PM Mostly Sunny 
Hi 56 Lo 44

Reith Riley had a 9 man concrete crew working on the the sidewalk and ramps on the South East corner of Martin Luther King and Washington Street. They then moved to the North west corner of MLK and Washington, and they finished up at the North west corner of Monroe and Michigan.

Reith Riley had a 3 man crew working on the Brick on Main street from Washington to Jefferson on the west side of the road 

Reith Riley had  a 3 man crew working on prepping and clean up  the South East and South west corners of MLK and LaSalle  and at various locations throughout the project.

Pemberton Davis had a 7 man crew working on push ped foundations at Colfax and MLK. Light Foundations at MLK and Wayne and conduit on the south west corner of Jefferson and MLK.

Wisco worked on the irrigation on the east side of MLK from LaSalle to Washington. 

Indiana Earth worked on removals at the North West corner of MLK and Washington, the Milton home and the intersection of Navarre and Michigan. 

No comments:

Post a Comment