Wednesday, December 7, 2016

12-7-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy  PM Cloudy 
Hi 37 Lo 27

Reith Riley has a concrete crew working on ramps at the south west corner of Main and Western. They have a second crew working on the south east corner of Jefferson and Saint Joe at the Century center. A third crew is pouring in the water preventer valves for the irrigation and various pieces on Michigan from Washington to Navarre.

Reith Riley had a brick crew working on Main street on the east side from Colfax to LaSalle cutting. A second crew was working from ColFax to Washington cutting and placing brick. A third crew was working from Jefferson to Western placing stone on the east side of Main for brick subbase.

Slussers was on site planting trees on the west side of Main from LaSalle to Western,

Pemberton Davis was stinging cable and setting heads at the intersection of Jefferson and Saint Joe.