12-5-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Cloudy PM Mostly Cloudy
Hi 38 Lo 32

Reith Riley had a Concrete crew working on the South West corner of Western and Main. A second crew worked on the South east and North east corners of Main and Monroe. 

Reith Riley had multiple crews working on the brick on Main street from LaSalle to Western on the east and west side of the road. 

Pemberton Davis moved the Tesco at Western and Main. They also worked on pouring the foundation at Jefferson and Saint Joe.

Indiana earth began filling in side walk areas that could not be finished this year.

Air Marking was in and did more grinding on Sample Street east of Michigan