3-2-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy snow squaws PM Cloudy Snow Squaws 
Hi 38 Lo 26

Pemberton Davis worked on putting in the Foundations for the traffic lights on the south west and North west corner of Washington and Saint Joe. They also worked on street light foundations between Washington and Jefferson on the west side of the road. They also poured the foundations for the traffic signal Cabinet and Tesco at the corner of Washington and Saint Joe. South east corner.

Thursday 3-2-17

    MLK and Washington; drilling and digging for foundations. 

no other work took place today.