Thursday, March 9, 2017

3-9-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM sunny PM Cloudy
Hi 42 Lo 32

Pemberton Davis worked on pulling wire on the west side of Saint Joe from Washington Street South. They also worked on the actuation on the intersection of Washington and Saint Joe/ MLK and getting the walk waits working. 

Thursday 3-9-17
    MLK and Washington; finished splicing cabinet, programed cameras , reset signs on spans , pulled in lighting cable in front of old H of F building and spliced poles. 

    Main St. Lighting; installed lighting cable at Washington, then between LaSalle and Madison. 

No other work took place today.