Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM sunny windy PM cloudy Windy
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM sunny windy PM cloudy Windy
Hi 32 Lo 25
Pemberton Davis worked on the street lights running East and west on Wayne street. They also worked on the street lights just north of LaSalle on the west side of the road. AEP placed the meter in the Tesco on the esat side of Saint Joe at Colfax.
Friday 3-10-17
Main St. Lighting; installed lighting cable at Wayne St. Area.
MLK lighting; installed conduit at LaSalle on NW corner and lighting cable
MLK signs; removed old St. Joseph and installed new MLK signs at several locations 2@ Jefferson, 2@ LaSalle. Removed and relocated existing signs as well.
No other work was preformed today.
MeetinG Minutes
Pemberton Davis worked on the street lights running East and west on Wayne street. They also worked on the street lights just north of LaSalle on the west side of the road. AEP placed the meter in the Tesco on the esat side of Saint Joe at Colfax.
Friday 3-10-17
Main St. Lighting; installed lighting cable at Wayne St. Area.
MLK lighting; installed conduit at LaSalle on NW corner and lighting cable
MLK signs; removed old St. Joseph and installed new MLK signs at several locations 2@ Jefferson, 2@ LaSalle. Removed and relocated existing signs as well.
Meeting With:
|
|
Meeting Date:
|
|
Regarding:
|
|
Construction and
Utilities
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1. Reith Riley :
Pemberton Davis will be focusing on the intersections of Main and Monroe and
Main and Western Next week. They will move to Michigan and Western along with
Michigan and Monroe the following week.
Around the 20th of March they will start back with a brick
crew and Wisco will be back onsite, try to get Air Marking in and have Indiana
earth in and working. The concrete crews will start back up the 3rd
of April.
Utility Relocation Issues:
AEP:
1.
Power at Colfax and Saint Joe east side meter:
After lengthy discussions with Mark Robinson of AEP over getting power and
meters to the tescos. He emailed back later in the day and the meter will be
placed at Colfax. It appears there is a disconnect with AEP and the building
department, the building department is not getting AEP the proper forms for the
new hook ups.
2.
Pole on Marion east of Michigan north side. Is
the responsibility of the last utility on the pole, which was Comcast.
Robert Henry:
1.
Manhole lid at Main and LaSalle: Robert Henry
not here today
Metronet:
1. WIFI on Saint Joe and Main Martell is working
at Washington and Main. They can now work at Washington and MLK. 50 % of the
antennas are up and working.
Transpo
1.
Signs mounted to bike Path: I will get a cost to
move the transpo signs to the brick area.
Utilities Q/A Toy asked to have Martel take the
Camera down at chase tower and return it to the City.
INDOT: Questions: Indot had no questions
Stakeholder Questions:
Larry asked about the cross walk at Bartlett. Tanner can not find the new
controller shipped to him. He asked about the lights between Bartlett and
Navarre, scheduled for the end of the Month.
Action Items
1.
Additional Asphalt Paving: The additional
paving of Wayne and the riverside neighborhood was put on hold due to the
pricing increase.
2.
Chase Tower sidewalk: the sidewalk around
the chase tower will be available April 1 per Toy.
3.
Guardrail at underpass on Main Street.: I
will contact Ryan from Structure Point and check on the status of the change
order( he expects it to be done later today)
4.
Pave Drain low: Josh will compile the data
that has been collected and the City will get together and will hold a meeting
later next week on the subject.
5.
Majority Builders Sidewalk work: This is
still in negotiations with City( Jitin is working on it)
6.
Landscape work: trees are being dug and
Slusser plans to plant trees in April and the landscape flowers in May. They
will fix the leaning trees in the downtown area by bracing them to the tree
grate. They will put flagging on the wires to illuminate the trip hazard.
7.
Unsafe list: Reith Riley will address
these issues if a real threat is current. They feel this is more of a list of
work not completed.
Reith Riley Construction
Concerns/Questions
Reith Riley needs to send pictures and a letter detailing
Main Street Row damage caused by the building contractor. Pemberton Davis
questioned the Bike signs, and is going to submit to me a new markup for
consideration. I will talk with ED Gleckler on the placement of the MLK signage
on Saint Joe Street
City
Concerns/Questions:
The lighting under the viaducts will start as soon as the
lights show up in a couple of weeks.
The City would like to see Pemberton Davis put more manpower
on the job, due to the schedule not staying on time. Street ID signs will be
placed once all underground work is completed.
Next weekly progress meet 3-24-17
No comments:
Post a Comment