Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy PM Partly Cloudy
Hi 54 Lo 42

Pemberton Davis 7 man crew with 1 boom truck an auger truck and 2 pickups 1 arrow board. Pembeton Davis `closed the North Bound Lane of Michigan Down North of Bartlett to work on placing the foundations for the street lighting on the east side of Michigan. They also took the Mast arm down at Colfax and Main South west corner.

Reith Riley had a 2 foreman and 2 Laborer 2 saws and 2 trucks placing permeable brick between the road and sidewalk on the east side of Main street from Wayne Street to Western.

Reith Riley had a second crew 1 foreman 1 laborer 1 teamster 1 operator 1 track hoe 1 flatbed 1 foreman truck prepping the side walk and ramps at the intersection of South street and Michigan. They then worked on the intersection of Main and Western South East corner, then did the sidewalk on the west side of Main North of LaSalle

Indiana Earth moved in today with 1 laborer 1 operator and 1 teamster, 1 track hoe 1 pickup and 1 tri-axle. They removed light pole foundation at Colfax and Main North west corner then moved South on Main Street to the South west corner of Main and Washington then to Wayne and Main.