Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy PM Cloudy
Hi 64 Lo 47

Reith Riley had a prep crew working on digging out for crosswalks at Madison and Main South east corner and the North West, South east corner of Western and Main. They also preped for sidewalk and brick on the North east corner of MLK and Western 1 teamster 1 foreman 1 opp 1 laborer 1 pickup t flatbed 1 track hoe

Reith Riley had a crew placing brick on the east side of main street between Jefferson and Main. They then started working on the east side from Wayne to Western. 2 foreman 3 laborer 2 trucks 2 generators 2 saws

Pemberton Davis worked on the intersection of Western and Main moving the traffic controller cabinet, rewiring the signal heads and pulling new wire for the signals. They took the old mast arm down at Jefferson and Saint Joe on the north west corner and took it to Western and Main and placed it on the north west corner for the signal that was struck earlier.  6 man crew with 2 bucket trucks and 1 foreman truck 

Wisco had a plumber working on the corner of LaSalle and MLK placing the stub for the sprinkler system.

Hard Core was on site to place the  storm sewer liner for the repair work that the light foundation hit at the intersection of Bartlett and Michigan.

No other work took place today.