Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Sunny PM Mostly Sunny
Hi 54 Lo 38

Pemberton Davis 7 man crew with 1 boom truck an auger truck and 2 pickups 1 arrow board. Pembeton Davis `closed the South Bound Lane of Michigan Down from North Shore to Bartlett to work on placing the foundations for the street lighting on the west side of Michigan. They then went and removed the last of the mast arm poles at Washington and main and Jefferson and Colfax. 

Reith Riley had a 2 foreman and 2 Laborer 2 saws and 2 trucks placing permeable brick between the road and sidewalk on the east side of Main street from Wayne Street to Western.

Reith Riley had a second crew 1 foreman 1 laborer 1 teamster 1 operator 1 track hoe 1 flatbed 1 foreman truck prepping the side walk at Main and Colfax North West Corner. They also worked on sanding in the brick on the east side of Main Street from LaSalle to Washington

Reith Riley had a third crew 3 foreman and 1 Laborer pouring concrete sidewalk on the North west corner of Main and Colfax. They then went down to Monroe and Main Street on the South east corner and poured the ramps.

Indiana Earth Not on site today due to broken down equipment.

Slussers had one man on site straightening up trees on main street.