Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 86 Lo 65

Rieth-Riley had a concrete crew that poured the remaining sidewalk on the west side of Main St. in front of the Madison Oyster Bar. Then they poured sidewalk on the west side of Main between Marian and Madison. 

Rieth-Riley also poured the concrete circle around the center pedestal of the Bartlett roundabout.

Rieth-Riley's grading crew was grading sidewalk on the west side of Main St. between South and Bronson.

Pemberton Davis was running conduit on at the intersection of Main and Jefferson. They also set handholes at Main and LaSalle.