Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 75 Lo 54
Weather Am Mostly Cloudy PM Mostly Cloudy
Rieth-Riley had a concrete crew pouring the southbound lanes of Main St between Bronson and South. Pavement was poured from Line MAI Sta. 717+47 to Sta. 720+30. In the afternoon the crew set forms for the next section of concrete which will be the southbound lanes directly north of what was poured today.
Ziolkowski was on site at the Marian roundabout pouring concrete foundations for the roundabout center walls. They also continued stripping forms from the walls at the Bartlett roundabout.
Ziolkowski started forming the wall at the Oyster Bar
The weekly progress meeting was held this morning. Meeting minutes are attached.
Meeting With:
|
|
Meeting Date:
|
|
Regarding:
|
|
Construction and
Utilities
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
·
Update: This past week, the walls at the Bartlett
roundabout were poured and forming for the walls at the Marion roundabout began. In the downtown area, Woodruff has been
placing finishing touches on pipe and structure work as Pemberton Davis
continued pouring mast arm foundations and pulling traffic signal conduit. Rieth-Riley poured curb on the west side of
Main between Lasalle and Colfax early in the week. On Thursday (7/14), their paving crews moved
into the west side of Main between South and Bronson streets to begin placing
concrete under the bridge. At Chippewa,
paving of the roundabout was completed and paving of crosswalks began. North of the roundabout, milling from
Chippewa to Ewing on Michigan Street began today (7/15).
·
Upcoming:
Next week, Rieth-Riley plans to continue pouring sidewalks at both the Bartlett
and Marion roundabouts. At the Marion
roundabout, more curbs and approaches will also be graded and placed. Early next week, Rieth-Riley is scheduled to
begin milling between the Marion and Bartlett roundabouts before continuing the
milling operation north of Bartlett to Angela Street. Upon finishing the milling operation, the new
surface will be placed towards the end of the week. Downtown, more curb will be placed working
south of Colfax Street on the west side of Main. Paving of the west side of Main between South
and Bronson Streets is set to be completed early next week. On Tuesday (7/19), Rieth-Riley may begin
restricting traffic to one lane in the downtown area to begin removals on the
east side of Main Street. At Chippewa, milling
and paving will continue on Michigan Street from Chippewa to Ewing. Placement of sidewalks and curbs will also
continue throughout the week next week.
Utility Relocation Issues:
AEP: SE corner of Chippewa
down guide in the sidewalk needs relocated. Rich also mentioned an AEP service that may
have been damaged at Donmoyer – he called about having someone come to check on
it, but he has not yet heard anything.
Robert Henry: Jimmy relayed
that Robert Henry has finished their work on the north side of the job. They finished patching their work on Western
earlier this week and will move to Washington Street starting Monday
(7/18). There they have about 3 days of
work to do from Main Street to Lafayette.
NIPSCO/InfraSource: Phil was able to complete the taps he had
scheduled this week, but unfortunately he still has stops to do. He’s now on schedule to have this work
completed by Monday (7/18), but he can’t guarantee this will be the case.
Comcast: Jay didn’t show.
AT&T: Tony hasn’t yet
heard back from Dennis regarding the pedestal at the bill board near Marion
Street. It needs to be relocated or
abandoned, but the lines may still be active since they are still being marked
by the locate crews.
Water Dept.: There was a
discussion today regarding how valve adjustments will take place as we move
from areas of full pavement removal to mill and fill areas. Where full removal was taking place,
Rieth-Riley has been replacing valve boxes with new ones provided by the Water
Dept. In mill and fill areas, however,
replacing these valve boxes becomes a whole new task. Further, in the mill areas on the plans,
there are many water castings that are not accounted for that will most likely
need to be adjusted to grade. Regarding
the Water Department’s downtown office, Tony assured Emily that their drive
will be replaced with stone immediately following its demolition next
week. Pat brought up a hydrant relocate
that needs to take place on the NW corner of the Chippewa roundabout.
Transpo: The South St.
driveway is set to be placed next week.
When traffic is switched to the west side of Main Street, however, buses
will not be able to turn east onto South Street. Instead, they’ll need to detour to Sample
Street and take Michigan back up to their new South Street approach. Tony stated that this traffic switch is set
to take place in about two weeks.
Metronet: Ben relayed that Martell
is awaiting the delivery of a part necessary to repair the busted conduit at
the intersection of Main and Jefferson.
He hopes to have this part and repair work done by the end of next week. After Ben left, Toy decided that a 2” conduit
will be run on the east side of Main instead of a 3” conduit. This conduit has already been ordered and
this decision avoids the need to bore on the east side of the street.
MCI : Tony has been
coordinating with Quentin regarding any MCI relocates that need to take
place. So far, there haven’t been many
issues save for a few adjustments of castings to grade on the west side of Main
Street.
INDOT: INDOT didn’t have any
questions or concerns.
Stakeholder
Questions:
JMS Building: Toy planned to
meet with the construction manager of the JMS Building later today to discuss a
work schedule for the coming weeks. To
complete their vault work, they require 5 – 6 working days with a lane and a
half on the east side of Main, which may conflict with Rieth-Riley’s plans to
begin removing the east side of Main next week.
Further, JMS is planning to pull street lights surrounding the building
and the pedestrian pole on the corner of Main and Washington on Tuesday.
10:00 am 10:10 Break Utility
and Stakeholders can leave
Submittals (List
at Meeting):
Action Items
1. Strain Pole Change Order: Myron will
get a message to Corbitt and then get it out.
2.
Saigon
Drive and Parking Lot: Roger relayed that the City and Rieth-Riley should
have a design back by this afternoon.
Scott asked that some verbiage be added to the change order regarding
the request that the work occur on a Monday.
Tony did bring to light some concerns about working around the schedules
of everyone else, ultimately impeding their ability to make progress.
3. Work
at Madison Oyster Bar: Ziolkowski
placed the wall at the Oyster Bar today.
Flow-filling should be finished by the end of next week.
4. Signal
Cabinets/status: Tanner stated
that he is awaiting a response from Traffic Controls Corp. He will follow up after the meeting, as will
Roger. Following from this conversation,
there was a discussion regarding utilities and storm pipe conflicting with the
proposed locations of mast arm and cabinet foundations. A list of these locations will be compiled so
that further action can be taken.
5. Crosswalks
on Side Streets: I believe
we’ve finally gotten caught up on placing all of these. Moving forward, I asked Tony to keep an eye
out when we take out crosswalks to make sure there is at least one means of
crossing each way across the street.
6.
Work
on East side of Main/shutting down: Toy decided that demolition of the east
side of Main can begin and traffic can be restricted to one lane. Looking forward, we’ll need to start thinking
about side street traffic…?
7.
Inlet
Structures at Chippewa Roundabout:
It was decided that the structures in question will be tack-welded and
the edges beveled. This way, traffic can
begin traveling on the structures and a decision can be made at a later date
regarding whether or not changes need to be made to avoid damage to the
roadway.
8.
Curb on
Main: Some curb and some sidewalk may need to come
out around the handicap area on the west side of Main between Lasalle and
Colfax to accommodate for the errors in elevation. Roger would like to get a new crew from JPR
to topo the entire job so that such problems can be avoided in the future. Tony was given the go-ahead to continue placing
curb. In the meantime, however, I’ll be
on site with the survey crew to fix any problems before they take place.
Reith Riley Construction
Concerns/Questions:
·
Pat requested some direction regarding how the
City would like to move forward with the permanent pavement striping beginning
next week from Ewing to Chippewa on Michigan Street. It was decided that all striping can be done
except for the center yellow stripe to avoid any confusion about whether or not
the street is open to two-way traffic.
Looking forward, Roger would like to meet next week so that we can begin
thinking about the work required and a potential date for opening this section
of Michigan Street to two-way traffic.
·
Tony mentioned that he was still awaiting an
answer regarding the hospital’s fiber vault.
City
Concerns/Questions:
·
Toy wanted to bring to Rieth-Riley’s attention
the fact that there will be more activity around the Marriott Hotel in the
coming weeks as their work begins.
·
Tanner with Pemberton Davis requested to receive
the signed warranty for the crosswalk systems at the Marion and Bartlett
roundabouts. Without it, the warranty is
reduced from 5 years to 1 year. Though I
have emailed the City office, I have not yet gotten a response. Further, Tanner relayed that he was still
waiting on D-sign designs.
Next weekly progress meeting 7-22-16
No comments:
Post a Comment