Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 89 Lo 71
Weather Am Mostly Sunny PM Sunny

Ziolkowski poured the center monument foundation and all concrete walls in the center of the Bartlett roundabout. They will take down all bracing tomorrow and remove formwork on Thursday (7/14).

Rieth-Riley had a concrete crew poured curb and curb and gutter on the northwest corner of Colfax/Main, the southwest corner of LaSalle/Main, and on the west side of Main between Colfax and LaSalle.

Rieth-Riley's grading crew laid patching asphalt on Michigan St. between LaSalle and Madison.

Woodruff had a crew finishing storm structure work on the west side of the intersection of Western/Main. They will move to Washington and Main tomorrow (7/13).

Indiana Earth was removing pavement on Main between Washington and Colfax. They also removed curb and sidewalk from the southwest corner of Main and Western and curb from the northwest corner of Main and Washington.

Pemberton Davis was working on lights on the southwest corner of the Bartlett roundabout.