7-9-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 72 Lo 57
Weather Am Mostly Cloudy and Humid  PM Mostly Sunny

Rieth-Riley had a concrete crew pouring sidewalk and curb ramps west of Michigan near the Bartlett roundabout. After completing two curb ramps and a section of sidewalk the crew moved to the Marian roundabout and poured the sleeper slab in the southeast quadrant. Crews worked from 7:00 am to 12:00 pm.

Rieth-Riley has an asphalt crew laying binder and the intermediate layer on Marian and Main along Line PR-A from Sta. 17+00 to Sta. 22+45.