Thursday, July 14, 2016

7-14-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 84 Lo 66
Weather Am Mostly Sunny PM Mostly Sunny

Rieth-Riley had a concrete crew which poured the southbound lanes of Main St. from approximately Line MAI Sta. 716+26 to Sta. 717+47. In the afternoon they set forms for the next section north. 

Woodruff installed a water valve in the center of Madison St. just west of Michigan. They then moved to Washington and finished the storm structure work at the northwest corner of Main and Washington.

Pemberton Davis set a handhole at the northwest corner of Main and Jefferson. They ran conduit across Jefferson on the west side of Main St. 

Ziolkowski stripped forms from the Bartlett roundabout walls. The rest of the forms will be taken off tomorrow. They also tied and set cages for the concrete foundations of the Marian roundabout walls. JPR provided revised drawings to the wall at the southeast corner misses the existing manhole.

Indiana Earth was not observed on site today.

Patrick Wooden from Structurepoint was on site viewing the Saigon market lot and the new sidewalk and curb on main between LaSalle and Colfax. Game plans were made for both of these issues.