Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 8/10
Hi 84 Lo 66
Weather Am Storms before 7, Light Rain  PM Sunny and Humid

Rieth-Riley crews pulled off this morning due to rain. Sporadic, light rain occurred during the morning and no rain happened after 11 am.

Woodruff had a crew installing storm pipe and structures at the intersection of Main and Wayne on the west side. They were also installing fire hydrants at this intersection and the water department decided to remove the hydrant at the southwest corner.

Indiana Earth continued curb removal on the west side of St. Joseph between Washington and Jefferson. Then they moved to the intersection of Main and Jefferson and performed pavement removal.  Grading was conducted at the intersection of Main and Bronson and saw-cutting also took place on the south side of South St. between Main and Michigan for the Transpo approach.

Pemberton Davis ran conduit from the center of Colfax west of Main to the handhole at the northwest corner of the intersection.


A meeting took place between City Engineering, Rieth-Riley, and JMS to coordinate JMS work at the northeast corner of Washington and Main.