Tuesday, July 19, 2016

7-19-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 88 Lo 71
Weather Am Mostly Sunny PM Sunny, HOT

Rieth-Riley had a concrete crew pouring pavement on the southbound lanes of Main St. north of South St. Pavement was poured from Line MAI Sta. 722+70 to 723+60. They also poured the South St. approach for the Transpo lot. In the afternoon they formed the south side of South St. west of Main for concrete pavement.

A second Rieth-Riley crew poured curb on the northeast corner of the Marian roundabout and the splitter island and curb on the north roundabout approach. The majority of curb for the Marian roundabout has been completed.

Indiana Earth had a one man crew saw cutting on the east side of Main St. between LaSalle and Washington. Another Indiana Earth crew was removing pavement on the west side of Main south of Madison Oyster Bat and north of Washington. Indiana Earth also graded the center of the Marion roundabout in the area inside the roundabout walls.

Pemberton Davis ran conduit for a signal cabinet and a Tesco cabinet at the southwest corner of Main and Washington.

Ziolkowski has finished stripping formwork from the Bartlett roundabout walls. Crews continued working on wall foundations at the Marian roundabout.

Reith Riley sealed the Oyster Bar block wall 