Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy light snow PM Cloudy light Snow  
Hi 22 Lo 18

Pemberton Davis worked on street lighting on the east and west side of Saint Joe. They assembled and set the lights from Jefferson to Colfax on Saint Joe and the 2 just north of Jefferson on the east side of Saint Joe. 

No Other work took place today. 

Phil @ Pemberton; "MLK Blvd lighting; installed lights on foundations north of Jefferson to Colfax. 
MLK and Washington; removed pedestrian signals and poles around the intersection." 