Thursday, February 23, 2017

2-23-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Foggy PM Mostly Sunny
Hi 62 Lo 42

Pemberton Davis worked on placing push ped foundations and walk wait foundations at Wayne and Main and at Washington and Main. They had a second crew working on splicing street lights on Michigan from LaSalle north to Marion. They then went and spliced street lights on the east side of Main Street from Wayne to Jefferson. 

Thursday 2-23-17
    Main St.; installed lighting and A-foundations. L- 1@ Washington, 2@ Wayne 
A- 1@ Washington, 1@ Jefferson, and 2@ Wayne. 
    MLK lighting; splicing poles. 

I contacted Slussers get get the trees straightened up on Main Street.

No other work took place today.