Friday, February 3, 2017

2-2-17


Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Partly Cloudy  PM Mostly Sunny
Hi 27 Lo 16

Pemberton Davis had a 7 man crew on site. They set the Tesco Cabinet and they moved the Controller Cabinet at the intersection of South an Michigan. They also strung new wire to up the strain poles. 

AEP showed up and ran power to the new Tesco that was completed around 1:00 PM. 

No other work took place today.

Phil @ Pemberton; "Michigan and South St. ; set pedestrian poles around intersection along with pedestrian signals and push buttons. Installed signal cable around the intersection and in SB mast arm. Set new signal cabinet and Tesco. Installed 3" and 1" conduit at Tesco cabinet."