Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny   PM Rain 
Hi 90 Lo 70

All work suspended when the rain started at 1:00 pm.

Pemberton Davis had a 1 man removing and adjusting Banner arms and street lights.

Pemberton Davis had 1 man grouting under Mast arms.

Pemberton Davis had 5 man crew working at the intersection of Monroe and Main placing a Hand Hole.

Wisco had a 4 man crew working at various location fixing irrigation.

Slussers had a 4 man crew working on punch list items dirt in planters, mulch river rock.

Rieth Riley finished tiling the building at Main and Western, They then worked on pouring miscellaneous pieces of concrete on the punch list.