Tuesday, January 24, 2017

1-24-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy PM Cloudy 
Hi 41 Lo 34

Pemberton Davis worked on the conduit for the lighting on Saint Joe from Wayne to Jefferson with a 3 man crew. They also worked on the traffic signal at Western and Main a truck hit the pole on the North west corner and forced them to get a pole from the City.

Robert Henry finished the work on Main Street for the AEP vault in front of TCU. The sidewalk is now open in that area.

I Met with Kara Boyles and Toy to bring her up to speed on the projects progress.

No other work took place today.


From Phil @ Pemberton; "MLK Blvd lighting; conduit runs north of Wayne to Jefferson. Also set pedestrian pole on SE corner at MLK and Jefferson. 
We also had a knock down signal pole at Western and Main that we had to replace and turn signals back on."