Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy PM Cloudy
Hi 41 Lo 34
Pemberton Davis worked on the conduit for the lighting on Saint Joe from Wayne to Jefferson with a 3 man crew. They also worked on the traffic signal at Western and Main a truck hit the pole on the North west corner and forced them to get a pole from the City.
Robert Henry finished the work on Main Street for the AEP vault in front of TCU. The sidewalk is now open in that area.
I Met with Kara Boyles and Toy to bring her up to speed on the projects progress.
No other work took place today.
Pemberton Davis worked on the conduit for the lighting on Saint Joe from Wayne to Jefferson with a 3 man crew. They also worked on the traffic signal at Western and Main a truck hit the pole on the North west corner and forced them to get a pole from the City.
Robert Henry finished the work on Main Street for the AEP vault in front of TCU. The sidewalk is now open in that area.
I Met with Kara Boyles and Toy to bring her up to speed on the projects progress.
No other work took place today.
From Phil @ Pemberton; "MLK Blvd lighting; conduit runs north of Wayne to Jefferson. Also set pedestrian pole on SE corner at MLK and Jefferson.
We also had a knock down signal pole at Western and Main that we had to replace and turn signals back on."