Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy Snow PM Cloudy Snow 
Hi 35 Lo 30

Pemberton Davis worked on the intersection of Jefferson and Saint Joe Street and got the Actuation going, they also worked on the street lighting on the east side of Saint Joe between Wayne and Jefferson.

The hand railing was installed at the Hospital today. 

Phil @ Pemberton; "MLK Blvd lighting; splicing poles. MLK and Jefferson; spliced new cabinet,Set more pedestrian signals and push buttons, remove old pedestrian signals. TCC programmed cameras and turned signals back on."