Friday, January 20, 2017

1-20-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy Rain PM Cloudy 
Hi 42 Lo 34

Pemberton Davis activated the walk waits and camars at the intersection of LaSalle and Michigan. The also worked on placing back plates on lights at Jefferson and Saint Joe and Colfax and saint Joe.

Robert Henry worked at the intersection of Washington and Main.

No other work took place.

From Phil Pemberton; "Jefferson and MLK; installed signal and camera cables around intersection. Put on more back plates to signal heads. TCC programmed cameras and pedestrian signals at LaSalle and Michigan." 