Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM light  Rain PM Cloudy light rain
Hi 50 Lo 41

Reith Riley hada concrete crew working the south west corner of Main and Colfax. A second crew worked on the North east corner of LaSalle and Saint Joe. 

Reith Riley had three crews working on placing brick on the west side of main between Wayne street and Washington. 1 crew placing stone, 1 crew placing brick, and 1 crew cutting brick.

Slussers had a crew working on grading for sod on Michigan between LaSalle and Marion on the east and west  side.

Pemberton Davis worked on the intersection of LaSalle and Saint Joe and they also worked on the intersection of LaSalle and Main. LaSalle and Main could not be completed due to the 5 conductor wire was run to the disconnects not 7.

No Air Marking on site today. 